Residential Street Repairs
- 768 sq.m of Masterscreed repairs
- 3¼ tonne of pre-patching material repaired potholes prior to the Masterscreed finish
- Work completed in 4 days
- Carried out with Stop & Go traffic control
Problem: Potholes and surface deterioration
Solution: Potholes and deep holes prefilled with Jointmaster™ IMP patching material (BBA HAPAS certificate 09/H149) then areas of deterioration coated with Masterscreed™ hot screed repair
Before
After
"Masterscreed provided a cost and time efficient method of carriageway repairs with minimal disruption to the public.
The Masterscreed system has also been used as part of the surface dressing pre-patching works, providing time and cost benefits to the overall programme”
Winter Damage Repairs
Potholed Surface
Screed and fill
Profile restored
Problem: Numerous potholes and patches had appeared following recent severe winters. They were so numerous that the additional resource was required by the council to treat them all in a timely manner.
Solution: Masterscreed was chosen as it quickly and safely restores the running surface, arrests further deterioration and recovers the carriageway profile.
- Over 11,000sq.m treated across 25 sites
- Average outputs of 110sq.m per day
- Smallest site 35sq.m. Highest output 250sq.m in a shift
- Sites fully open to traffic at the end of each shift
- Installed between March 2010 and February 2011
- No cutting out required. Just clean and fill
“The Rhino solutions for carriageway repairs and cracking have quickly and efficiently, with minimal disruption, enabled us to bring our network back to a safe condition for road users following two winters that have badly affected our roads”
Temporary repairs on a trunk road
Client: Essex County Council.
Site: A127 Southend Arterial Road heading westbound from Basildon towards the M25 junction.
Problem: The Stone Mastic Asphalt had deteriorated leaving a lean & hungry surface with some areas of potholing. The client was looking for a short to mid-term solution before carrying out more extensive reconstruction / resurfacing work.
Solution: Masterscreed was chosen for its ability to:
- Restore a safe running surface
- Arrest further deterioration
- Recover some of the carriageway profile
- Works were carried out over night between 21:30 hrs and 05:30 hrs
- 1,000 sq.m and treated in 5 nights
- The site fully open to traffic each morning before the rush hour
- Outputs of 200 sq.m per night
- Average Traffic Volumes 33,000 vehicles per day
Temporary repair whilst a permanent solution was sought
The problem at this location was the lack of time. Given the condition of the surface, it was due for resurfacing and sub-grade repairs but remained unfunded for the next 18 months.
A simple and quick solution such as Masterscreed, provided the all-important breathing space by extending the asset life, providing a safe durable finish, understanding that a permanent solution would eventually address the sub-grade issues.
The Rhino team were very responsive. They arrived when promised and carried out a fast and neat operation. The Masterscreed material helped improve the existing surface and was quickly applied to prevent disruption on the road
The Rhino solutions for carriageway repairs and cracking have quickly and efficiently, with minimal disruption, enabled us to bring our network back to a safe condition for road users following two winters that have badly affected our roads
Refurbishment of speed cushions
- 14 speed cushions completed in 2 shifts
- The major holes and defects were pre-patched
- A surface coat of Masterscreed was applied to the complete cushion
Five road humps repair in one night shift outside a school
A fast and effective repair was needed to restore 5 road humps in Lewes Town Centre. The solution was Masterscreed. Initially the potholes were patched and repaired with the hot applied Masterscreed material, before treating the whole surface with a screed of the same material.
5 road humps in Lewes town were treated in a single overnight road closure and were completed in less than 4 hours.
Village Gateway in Red
A village gateway was required in Ringmer, East Sussex and we applied a red Masterscreed to this section of road to alert drivers to the presence of a speed reduction area.
M4 Bus Lane
Masterscreed in red was used to message the drivers that this area was not an additional lane, but instead an area that was not to be driven on.
Mixture of repairs in red and black: A22 Forest Row
Masterscreed was chosen here based on previous experience and performance. Designed to hold and delay resurfacing, Masterscreed provided a durable alterative to full resurfacing
- There were 44 patches along 600m of site (2,181m2)
- Works were delivered over 5 night shifts with multiple crews where needed
- A mixture of red Masterscreed for the coloured surfacing areas and black for the maintenance repairs